Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.

In 2019, Edgewood Middle School underwent renovations and expansion, including the construction of a new parking lot. To utilize the available property, a wall was needed to create a level surface area for the parking lot.
PROPEX® Pyrawall®, an engineered wrap-face vegetated solution for constructing reinforced-soil walls and steepened slopes, was selected to reach the desired grade. Initially a modular block wall was considered, but PROPEX Pyrawall was selected because it was a more cost effective and environmentally friendly solution.
Eight, one foot, PROPEX Pyrawall lifts were constructed to raise the grade for the new parking lot. The wall was fully vegetated within four months of construction, and now blends with the current landscape.

Edgewood Middle School, Minnesota Slope stabilization PROPEX Pyrawall

Edgewood Middle School, Minnesota Slope stabilization PROPEX Pyrawall

Edgewood Middle School, Minnesota Slope stabilization PROPEX Pyrawall
Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Runway overrun area, La Guardia International Airport, New York, USA
La Guardia Airport built a 150 m by 230 m runway overrun area on soft inter-tidal clay using staged construction, high-strength geotextile reinforcement, hydraulic sand fill, and PVDs to prevent mud waves and accelerate consolidation.
Flood protection for Reinland Drain in Manitoba
PROPEX® Armormax® stabilized the eroded Reinland Drain, reducing costs and emissions while ensuring long-term flood protection with reinforced vegetation growth.