Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
The Riverside Industrial Complex project in Chino, California involved the construction of four new commercial/industrial buildings, with sizes ranging from approximately 89,100 ft² (8,281 m²) to 789,084 ft² (73,319 m²). These were designed as single-story structures made from tilt-up concrete, and all except for the one located in the southeast section of the site featured truck docking areas. The buildings were surrounded by asphalt and Portland cement concrete pavements. To reach the intended ground levels for this development, fills of between 2 ft (0.61 m) and 30 ft (9.14 m) were required.
In the areas previously utilized as detention ponds, extensive excavation was recommended prior to the introduction of new fill material. Soil assessments at the boring locations showed that the existing soils in the proposed building areas needed to be excavated to a minimum depth of 3 ft (0.91 m) below the planned foundation elevation, or 4 ft (1.22 m) below the existing ground level, whichever was greater. Very moist or wet soils were anticipated at the base of these over-excavations. SCG provided preliminary recommendations for subgrade stabilization in their soils report. The stabilization process involved laying down a permeable, durable geotextile fabric (MIRAFI® RS380i) over at least an 18 in (45.72 cm) layer of crushed stone, with particle sizes ranging from 2 to 4 in (5.08 to 10.16 cm).
The application of the MIRAFI RS380i geotextile fabric greatly enhanced the extremely poor subgrade conditions, allowing for the creation of a stable platform. The MIRAFI RS380i geotextile provided:
Superior tensile strength that supported the subgrade effectively.
A separation layer that prevented the mixing of poor native soils with the aggregate base.
Filtration that managed water from the saturated soils efficiently.
Lateral confinement that maintained the integrity of the stone base.
Furthermore, this geotextile remained intact during the placement and compaction of the angular 2 to 8 in (5.08 to 20.32 cm) crushed concrete. The result was a robust and stabilized platform, suitable for the construction of the four commercial buildings, along with the associated parking lots and loading docks.
Construction of four large-scale commercial and industrial buildings, ranging from 89,100 to 789,084 ft2 featuring advanced tilt-up concrete design
Efficient water management and lateral confinement maintained by the geotextile fabric, supporting the integrity of the stone base during construction
Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Runway overrun area, La Guardia International Airport, New York, USA
La Guardia Airport built a 150 m by 230 m runway overrun area on soft inter-tidal clay using staged construction, high-strength geotextile reinforcement, hydraulic sand fill, and PVDs to prevent mud waves and accelerate consolidation.
Flood protection for Reinland Drain in Manitoba
PROPEX® Armormax® stabilized the eroded Reinland Drain, reducing costs and emissions while ensuring long-term flood protection with reinforced vegetation growth.