When a prominent developer and operator of renewable energy storage solutions was building a new solar site in Texas, a solution was needed to stabilize access roads used during installation. Solar farm sites are often located in remote, protected areas or agricultural land, where soil conditions can be less than ideal.
Multiple access roads needed to be constructed to allow heavy machinery and materials to be transported to the construction site. Expansive soils, which can shift and change volume with moisture fluctuation, created challenges in stabilizing these access roads.
After evaluating various options, the engineering team chose a solution involving six in. (15 cm) of flexible base over MIRAFI® RS380i. MIRAFI RSi-Series provides a proven solution for constructing durable, high-performance access roads and platforms in solar farm projects.
Taking the soil conditions into consideration, the required reduced aggregate thickness for road stabilization was determined using the subgrade strength parameters outlined in the Giroud-Han (2004) methodology. This approach provided the necessary reinforcement for the access roads while reducing material costs, shortening the construction timeline, and ensuring long-term durability. Additionally, it minimized environmental impact by conserving resources and reducing CO2 emissions compared to traditional methods.
By utilizing the MIRAFI RS380i system, immediate site access was achieved without the need for excavation and allowed for a thinner base layer, resulting in substantial savings. The Solmax team provided onsite support during installation, visiting the site multiple times to address questions and proper installation criteria.

MIRAFI RS380i placed to reinforce access roads over expansive Texas soils.

Geotextile reinforcement installed to reduce base thickness for solar farm roads.

Access road construction accelerated using MIRAFI RS380i and flexible base

Field crew installing MIRAFI RS380i to improve bearing capacity.

Reduced aggregate layer achieved through Giroud–Han design methodology.
Rebuilding resilience: post-wildfire erosion control on Pacific Palisades bluff
A homeowner used PROPEX Armormax to protect a bluff damaged by the Pacific Palisades fire to reduce erosion risk, support revegetation and mitigate future wildfires.
Runway overrun area, La Guardia International Airport, New York, USA
La Guardia Airport built a 150 m by 230 m runway overrun area on soft inter-tidal clay using staged construction, high-strength geotextile reinforcement, hydraulic sand fill, and PVDs to prevent mud waves and accelerate consolidation.
Flood protection for Reinland Drain in Manitoba
PROPEX® Armormax® stabilized the eroded Reinland Drain, reducing costs and emissions while ensuring long-term flood protection with reinforced vegetation growth.